Hidden defects in new housing – Judicial Expert in Construction


Hidden Defects in New Homes: How to Prove that the Defect Preexists Delivery

By Aurelio Tamarit Blay— Official Judicial Expert in Construction | +30 years in forensic expertise

"The delivery was impeccable: keys, receipt document, inauguration tape... But after 3 months, cracks began in the bathroom ceiling. After 5, dampness in the bedroom. After 5 months and 20 days, they told me: 'you can no longer complain'."

— Real case, Valencian Community, 2024.

These types of situations occurmore than you think. And most of the ownersthey lose their rights for ignoring a critical deadline: 6 months.

It's not a myth. It is thearticle 1,489 of the Civil Code:

“The seller is obliged to clean up hidden defects in the thing sold… The period to exercise the action is six months, counting from delivery.”

⚠️ importantes: This termIt is not suspended or interrupted due to attempts at dialogue with the construction company.. It is only interrupted with aformal extrajudicial or judicial claim.

🔍 ¿Qué se considera “vicio oculto” en construcción?

A vice ishiddenYeah:

  • Exists at the time of delivery
  • Not detectable by ordinary inspection
  • Makes the homeless useful or less suitable for normal use
Type of vice Visible on delivery? Real case (anonymized)
Filtration through flat roof without slope ❌ No (solo tras lluvia intensa) Housing in Alzira: roof leaks 4 months later
Shrinkage cracks in jointless slabs ❌ No (aparecen a los 3–6 meses) Building in Burjassot: vertical cracks in the party wall
Rising humidity due to lack of capillary barrier ❌ No (manchas a ras de suelo tras 5 meses) Floorin Valencia: mold on kitchen baseboard

Technical key: The expert opinion must demonstrate that the defectexists at the time of delivery(with typical patterns of early pathology, not wear).

📅 Tu cronograma de acción (¡antes de los 180 días!)

Day critical action Can you wait?
Day 0 Handover of keys + reception certificate
Day 30–60 Appearance of first symptoms ❌ No ignores “detalles”
Day 90 Confirmation of pathology → optimal moment for expertise ⚠️ Urgente: el reloj ya corre
Day 150 Issuance of report + extrajudicial notification ✅ Último momento seguro
Day 180 Expiry of the right ❌ Demasiado tarde

🧪 Qué debe incluir un informe pericial válido para vicios ocultos

For the report to have evidentiary value (STS 456/2022), it must contain:

  1. Chronological identification of the defect
    Ex: “The cracks have clean, unfilled edges, typical of recent cracking (<4 months).”
  2. Link with unfulfilled regulations
    CTE DB-SE, DB-SUA, DB-HE, EHE-08.
  3. Objective tests, not subjective
    Thermography, endoscopy, calibrated hygrometer.
  4. Clear expert conclusion
    “The defect is pre-existing upon delivery and is attributable to constructive deficiency, not to use or maintenance.”

📩 ¿Compraste una vivienda nueva y ves algo raro?

Don't wait for it to “get better with time.” The hidden vicesthey don't disappear on their own—they get worse.

  • Expert report valid for legal notification
  • Quote closed in ≤ 24 hours
  • Execution period: 72 hours (emergencies by deadline)

Request evaluation – Hidden Vices (before 6 months)